[PPSC SO (Teaching), SO (DNA),& SA (DNA) 2023]
35. Saket and Raashi work together on a project. Saket can alone finish the project in 24 days. Saket is twice as fast as Raashi. If they finish the project in 8 days with the help of Nitesh, in how many days Nitesh alone can finish the project?
16
20
10
12
Correct Answer :
16